Overview
In this process, the soil or rock is removed from the work area in order to prepare the site for construction. This can be done mechanically and manually too. You have to understand two technical terms in excavation: lead and lift. Lead is the horizontal distance from the point of excavation to the point of disposal. Lift is the vertical height through which the soil or rock has to be lifted.
There are two codes you should deal with to calculate the rate for excavation.
- District Rate
- Norms by DUDBC
You can find the details in our previous blog: https://www.ieccc.com.np/2024/06/cost-of-m20-grade-concrete-in-Nepal.html.
Let's deal with excavation cost analysis per cu. m. for different categories
of soil by manual and mechanical means.
- Soft clay and silty soil
- Hard clay and soils mixed with soft moorum stones (up to 30 cm in size)
- Medium rock
- Hard Rock
By Manual Means
Soft Clay
Earthwork excavation of soft clay and silty soils, including disposal of up to 10 m of lead and 1.5 m of lift |
||||||
Description |
Type |
Quantity |
Unit |
Rate |
Amount |
Remarks |
Workers |
Skilled |
0.00 |
Mday |
1185 |
0.00 |
|
|
Unskilled |
0.70 |
mday |
870 |
609 |
|
Tools and Plants at 3% |
18.27 |
|
||||
Sub Total |
627.27 |
|
||||
Contractor Overhead and Profit at 15% |
94.09 |
|
||||
Total |
721.36 |
|
Normal Soil
Earthwork excavation of hard clay and soils mixed with soft moorum stones (up to 30 cm in size), including disposal of up to 10 m of lead and 1.5 m of lift |
||||||
Description |
Type |
Quantity |
Unit |
Rate |
Amount |
Remarks |
Workers |
Skilled |
0.00 |
Mday |
1185 |
0.00 |
|
|
Unskilled |
0.80 |
mday |
870 |
696 |
|
Tools and Plant at 3% |
20.88 |
|
||||
Sub Total |
716.88 |
|
||||
Contractor Overhead and Profit at 15% |
107.53 |
|
||||
Total |
824.41 |
|
Medium rock
Earthwork excavation of medium rock, including disposal of up to 10 m of lead and 1.5 m of lift |
||||||
Description |
Type |
Quantity |
Unit |
Rate |
Amount |
Remarks |
Workers |
Skilled |
0.00 |
Mday |
1185 |
0.00 |
|
|
Unskilled |
3.00 |
mday |
870 |
2610 |
|
Tools and Plant at 3% |
78.30 |
|
||||
Sub Total |
2688.30 |
|
||||
Contractor Overhead and Profit at 15% |
403.24 |
|
||||
Total |
3091.54 |
|
Hard Rock
You should make use of a hydraulic excavator for earthwork in hard rock.
By Hydraulic Excavator
Particular |
Description |
Unit |
Time (Hours) |
Remarks |
Hydraulic Excavator |
Soft Soil |
Cu.m |
0.0163 |
|
Hard Soil |
Cu.m |
0.0200 |
|
|
Medium Rock |
Cu.m |
0.0277 |
|
|
Hard Rock |
Cu.m |
0.0370 |
|
Note: You need an extra tractor or dumper with an unskilled worker for mechanical means.
Others
Before excavation work, site clearance has to be done. Let's calculate the rate of site clearance per square meter.
Site Clearance
Site Clearance including vegetation cutting and surface dressing |
||||||
Description |
Type |
Quantity |
Unit |
Rate |
Amount |
Remarks |
Workers |
Skilled |
0.00 |
Mday |
1185 |
0.00 |
|
|
Unskilled |
0.01 |
mday |
870 |
8.70 |
|
Tools and Plants at 3% |
0.26 |
|
||||
Sub Total |
8.96 |
|
||||
Contractor Overhead and Profit at 15% |
1.34 |
|
||||
Total |
10.3 |
|
Note: The above-calculated price is exclusive of VAT.